Metrics and SLA Foundations for NaaP

Cloud SPE — Update #1

Period: January 1, 2026 – January 31, 2026

Status: On track

Summary:

Following the successful passage of our Treasury Proposal, we have established our core data infrastructure and completed a comprehensive inventory and quality validation of existing network data. These foundational steps ensure the accuracy of our analytics pipeline as we approach the completion of Milestone 1.

Completed Deliverables:

Milestone 1: Initial Infrastructure & Data Validation partial delivery - Feb 6 Due date

Built the initial infrastructure to support data ingestion, processing, and deployment to the analytics stack, resulting in a basic initial functional end-to-end flow to a basic Grafana dashboard.

ETA for Next Update: March 1, 2026

Planned by Next Update:

  • End-to-End Dashboard: Deployment of a public Grafana dashboard displaying several key live analytics metrics.
  • Data Integrity: Completion of all data quality validation and automated capture processes.
  • ETL Pipeline: Significant progress on the Extract, Transform, Load (ETL) processing pipeline to handle complex data transformations.
  • Infrastructure Stress Test: Validation of the current infrastructure’s stability and scalability to handle increased data loads.