Pre-Proposal: Network Engineering SPE

Network Engineering SPE — Update #1 (May 2026)

Period: 15 May 2026 – 31 May 2026

Status: On track

Summary: SPE launched on schedule, both funding lanes opened, and the first RFP ran end-to-end with a contract awarded within 11 days.

Completed Deliverables

Watercooler Presentations

Project Updates — Discord #📊│project-updates

Follow the discussions here

Planned by Next Update

  • RaidGuild Tranche 1 (audit plan + teardown scope) signed off.
  • More RFPs and grants.

ETA for Next Update: 30 June 2026